Udhampur-Ramnagar Road | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Imptt/UG of Udhampur–Ramnagar road | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Earthwork - 27 km completed out of 27.53 km.
Breast walls- 3766 RM completed out of 3785 RM.
Retaining wall - 6486 RM completed out of 6878 RM.
Side drains: 20555 RM completed out of 22000 RM. Hume pipe culverts -67 nos. culverts completed out of 67 nos. Slab culverts -15 nos. completed out of 21. GSB - 26.998 Km completed out of 27.530 km. WMM - 26.998 Km completed out of 27.530 km. DBM -26.68 Km completed out of 27.530 km. BM - 11.37 Km completed out of 11.37 km. SDBC: 7.2 km completed out of 27.530 km. Tawi Bridge: At abutment A1, 8 lifts completed out of 15 lifts. At abutment A2, raft is completed, 9 lifts completed out of 15 lifts. P1 - 2 lifts completed out of 15 lifts, P2 - 2 lifts completed out of 15 lifts, P3 - excavation in progress, P5 - Raft completed. Riti bridge : Sub Structure - Abutment A1 & A2 completed Riti bridge : Super Structure - i) Slab Casted Finishing work is in progress |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Road Udhampur-Ramnagar is located in Udhampur district taking off from Roun-Domail, 10 kms off Udhampur city which is located 67 kms from Jammu on National Highway-1A. | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||