Loan:
|
2925-IND |
Category: |
|
Location: |
Kashmir Urban Drainage |
Districts Passing: |
|
Constituency Passing: |
|
Status: |
Works Completed |
ERA Ref: |
JKUSDIP Srinagar/SWD/03 Type: Mode: |
ERA Pac ID: |
455 |
PCSS No: |
0028-03 |
Scope of Work: |
14 nos of pumping stations |
Contract Cost in Rs crore: |
30.263 |
Dynamic Cost in Rs crore: |
30.24 |
Contractor Details |
WPIL Limited |
Date of Signing of Contract |
14 September 2015 |
Date of Start of Work (NTP) |
01 October 2015 |
Completion Period |
(32 Months) |
Completion Date as per Contract |
31 December 2016 |