ERA Projects
J&K ERA Main Logo
Govt. of Jammu and Kashmir
  Jehlum Tawi Flood Recovery Project (JTFRP) | Search | | Admin |
Project Details
GO BACK
Wahibugh Bridge
Wahibugh Bridge
Wahibugh Bridge (Scope =95 m )

Loan:

2151-IND
Category: Engineers Design
Location: Kashmir Transport Bridges
Districts Passing:

Constituency Passing:

Status: Works Completed
ERA Ref: Transport Srinagar/Roads/26 Type:Works Mode: LCB
ERA Pac ID: 0044
PCSS No: 0077
Scope of Work: 95 Mts
Contract Cost in Rs crore: 2.6532
Dynamic Cost in Rs crore: 3.99
Contractor Details Sohrab Iqbal Goni
DDR Approve Date
DPR Approve Date
IFB Issue Date (Last) 31 October 2007
Technical BID Open Date 06 December 2007
Financial BID Open Date 09 January 2008
Letter of Acceptance to contractor (LOA) 13 February 2008
Date of Signing of Contract 15 March 2008
Date of Start of Work (NTP) 10 May 2008
Completion Period (15 Months)
Completion Date as per Contract 13 July 2009