Wanpoh-Chawalgam-Aharbal Road
Wanpoh-Kulgam & Tchawalgam- Nehama- Aharbal Roads (earlier 38 Km)
42.7 Km Road Completed and handed over to R&B Deptt

Loan:

2151-IND
Category: Engineers Design
Location: Kashmir Transport Roads
Districts Passing:

Constituency Passing:

Status: Works Completed
ERA Ref: Transport/Srinagar/Road 20 Type:Works Mode: LCB
ERA Pac ID: 0037
PCSS No: 0073
Scope of Work: 42.7 KM
Contract Cost in Rs crore: 26.8124
Dynamic Cost in Rs crore: 41.14
Contractor Details Hassan Const Company
Date of Signing of Contract 07 January 2008
Date of Start of Work (NTP) 01 April 2008
Completion Period (21 Months)
Completion Date as per Contract 30 December 2009
 
Project Completed and handed over to R&B Department on 08-01-2015